Construction Update: The Vines at Miravale
We’re pleased to share a fresh construction update from The Vines at Miravale, where steady progress is being made both inside and out.
External Works
- Upper feature cladding and painting to the upper levels have been completed
- Remaining scaffolding is being removed
- The alfresco roof is now installed, with ceiling works to follow
- Work on the lower Hebel, rendering, and feature cladding is progressing
- Carport slabs are still due to commence soon
Internal Progress
- First fix services are complete
- Insulation and internal wall lining have been installed
- Second fix carpentry is finished
- Undercoat painting has begun
- Waterproofing is complete
- Kitchen installations are on the horizon
- Stone benchtop measurements and tile deliveries are being scheduled
We’ll continue to keep you updated as things move forward on site. If you have any questions or would like to learn more about The Vines at Miravale, feel free to get in touch with our team.